Lake Hancock Lake Level Modification and Outfall Treatment Projects

Timeline

The preliminary project schedule for the Lake Hancock projects is shown below. The schedule will be periodically updated as progress is made.

Lake Hancock Lake Level Modification Project

Step 1: Evaluation
May 2003 – August 2004
Step 2: Preliminary design, engineering and conceptual ERP*
Aug. 2004 – June 2007
Step 3: Final design, engineering, individual ERPs & construction documents
Oct. 2007 – Dec. 2009
Step 4: Construction
June 2009 – December 2011

* Conceptual ERP was received from FDEP on June 14, 2007.


Lake Hancock Outfall Treatment Project

Step 1: Feasibility and selection of treatment method
February 2006
Step 2: Engineering testing, Design, ERP and construction documents
October 2009
Step 3: Construction and startup
December 2011
logoblk.gif